How do I bring modified Master Material Multipliers into a specific project?

Tip - When changes are made in the Masters, they are not automatically copied to existing projects. You must manually copy them using the procedures below.

To bring Master Material Multipliers into a current project, follow these steps:

  1. In the AutoBid Mechanical main window, click Reports
  2. Click Project Material Multipliers.
  3. Click the Copy/Save As button. 
  4. In the Copying Material Multipliers window, make sure Step 1 From Master is selected. 
  5. In Step 2, select the Update Multiplier Values only option button. This updates the values in your current project based on those changed in the masters. 

Note: If in Step 2 you select, Append any new Material Multiplier rows, only new values will be added to your project.